Underwater foundations
Contents |
[edit] Introduction
Foundations can often be required for the construction of harbour walls, sea walls, breakwaters, and so on. Underwater foundations, also known as subaqueous foundations, may be used in situations where the use of a cofferdam or caisson is prohibitively expensive or unfeasible.
Typically, dredgers or grabs working from pontoons will excavate the ground and load the spoil into barges. If rock needs to be removed, drill and blast methods can be used, or drilling and cutting by jackhammer. Softer rock formations can be dredged or broken up by air tools and then grabbed. Gravel and sands can be excavated using a suction dredger or ejector tube.
Divers can then place temporary steel formwork, using sandbags to anchor them in place and prevent concrete leakage from under the toe of the form. If the foundation is relatively short and in shallow water, bagged concrete or cement placed in layers may be used as formwork and left in position. Foundations in deeper water may incorporate permanent formwork in the form of precast concrete blocks which are tied in to the foundation.
The concrete mix must have a high degree of workability to maintain a good flow and prevent too much cement being washed out of the mix. This ensures that the leading edge of the concrete is kept moving forward under the pressure of additional material. Extra cement should be added to offset any loss through the water, although too much cement will result in excessive laitance forming on the concrete surface.
[edit] Concrete placing
Concrete is generally placed by one of three methods:
[edit] Placing by tremie
A tremie is a steel tube suspended in the water from a crane. A hopper is fixed to the top end to receive the concrete. The tremie is positioned vertically over the area to be concreted with the lower end resting on the bottom. After the pipe has been filled with concrete it is raised off the bottom to allow it to flow. This should allow the flow to continue to feed the interior of the initial mass.
The flow rate of concrete is controlled by raising and lowering the tremie, but care must be taken not to lift the tremie out of the concrete mass, otherwise the seal will be broken and the concrete will be weakened by water as it rushes out of the pipe. This may result in a damaged surface to the mass of concrete which will need to be removed before work can recommence. One tremie will serve an area of approximately 30 sq. m, and where all the concrete cannot be placed from one position, more than one tremie can be used for simultaneous placing.
For more information, see Tremie.
[edit] Placing by skip
Bottom-opening skips can be used, which are fitted with a top cover held in position by water pressure. The skip is filled with concrete before being gently lowered into the water. On reaching the bottom, the skip is emptied.
If it is lowered too rapidly, the covers may be disturbed and the concrete inside damaged. This is a slower method than a tremie pipe but can be more practical for thin beds, whereas tremies are more appropriate for large pours.
[edit] Pumping
Concrete pumping is a method used when very large concrete pours are required.
Pipe lines typically have a diameter of 110-150 mm and are generally capable of pumping for a distance of 300 m horizontally and 30 m vertically. Pumps may be mounted on a pontoon with an extendable steel boom. The pump works hydraulically with a diesel-driven piston that forces concrete along the pipes.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.